NYC DOB & DEP Submission Updates

The NYC Department of Buildings (DOB) has released an update to their application processing to limit the amount of walk-in traffic to DOB offices in response to the COVID-19 emergency declaration, effective as of March 18, 2020 until further notice.

In brief, DOB is encouraging customers to continue to use self-servicing online tools such as eFiling and DOB NOW: Build for all Hub Development, Full, Self-Service jobs, After Hour Variance (AHV) permits and applicable work types.

For the below transactions with payments that cannot be processed in eFiling or DOB NOW, the customer shall mail the application to the appropriate borough office and include on the envelope Attn: Application Processing. Attach to the application a check or money order for the amount owed payable to the NYC Department of Buildings. The application can also be hand-delivered to the borough office where there will be a designated drop-off box.

PW1 Approvals or Objections:

Applicants/customers shall send PW1 approvals or objections by e-mail. Note the plans will not be returned by e-mail and will be required to be picked up from the borough office by pulling a service ticket.

L2 Requests:

L2 Requests for Overrides, Reductions or Waivers of Civil Penalties for civil penalty paid or no relationship to the violation can be included with the permit application. All other L2 requests shall continue to require a visit to a borough office in-person.

Post Approval Amendments (PAA) and Supersede Requests:

PAA applications and supersede requests filed in-person shall be dropped off at the borough in the designated drop-off box. Payment is due in-person at the borough office only after the PAA status in the Building Information System (BIS) is PAA Fee due.

Please review the full DOB Application Processing Update with locations for Mail and Drop-off Transactions here.

Also, to keep up with the latest DOB updates in response to COVID-19, visit DOB COVID-19 Updates.

NYC Department of Environmental Protection:

The Department of Environmental Protection (DEP) recently released clarification of the application and testing submission process that will be used during the COVID-19 Emergency Declaration. In general, the DEP will be following the following procedures until further notice:

In addition, each type of submission has been provided with the following added procedures in order to streamline the application process:

Cross Connection Applications (Backflow Applications):

Backflow Initial Test Reports:

Site/House Connection Proposals:

Failing to comply with the guidelines set forth above could result in project delays.

Fire Department of New York
The Fire Department of New York (FDNY) has issued temporary procedures to accommodate submission of plans and resubmissions in response to the COVID-19, effective as of March 31, 2020.

The Plan Intake Unit of FDNY will accept the following plans and resubmissions by e-mail: